Top storiesNew ZealandPoliticsBusinessEntertainmentSportsWorld

Transmission Gully route to open by Christmas, with $1 billion price tag

Friday, 14 February 2020

The Transmission Gully motorway north of Wellington was due to open in late 2020.

Transmission Gully is now officially a $1 billion road after delays saw another $190 million added to its bill.

But the road, sought for decades, does now have an official opening time.

The NZTA announced the previously $850m project would now be opened by Christmas this year, however it had to provide the cash to builder CPB HEB JV as relief after construction problems.

The agency confirmed the cost to build the road, including the new payment, was now $1.041 billion.

A Transmission Gully bridge takes shape, in September, 2019, despite delays in the overall project.
A Transmission Gully bridge takes shape, in September, 2019, despite delays in the overall project.

**READ MORE:

November date revealed for completion

Gully hits stumbling bock

Legal action over Gully project**

Transport Minister Phil Twyford would not comment on the announcement of the new opening time or the additional spending.

NZTA's interim chief executive Mark Ratcliffe said the settlement would ensure Transmission Gully was completed to a high standard, met the needs of customers and achieved good value for money.

NZTA has released flyover photos from the Transmission Gully expressway project near Wellington.
NZTA has released flyover photos from the Transmission Gully expressway project near Wellington.

Last year Stuff reported that the NZTA planned a potential November opening for the road, pushing back its original completion time.

Construction began on the 27 kilometre-long road in 2015, with April 2020 initially touted as the month traffic would finally flow onto four-lanes connecting Linden in north Wellington to Paekākāriki on the Kāpiti Coast.

Then the NZTA agreed to a one-month extension of the project's planned completion date – to May 2020 – but didn't rule out more delays.

Ratcliffe said the site's challenging conditions had impacted the construction. 'The project required an increased earthworks programme, creating further complexity, disruption and cost to the project through the additional consent requirements.'

He said those problems and the impact from several storm events and the Kaikōura earthquake meant CPB HEB JV 'has incurred significant additional costs to construct the project'.

Photos of the progress on Transmission Gully taken by Leo Cooney in December 2019
Photos of the progress on Transmission Gully taken by Leo Cooney in December 2019

'In acknowledgement that these issues were out of the control of CPB HEB JV and not something they could have reasonably anticipated the Transport Agency has provided $190.6m of financial relief.'

As part of the settlement, CPB HEB JV's historic claims against the Wellington Gateway Partnership, the public-private contractor, and NZTA were resolved without resorting to court action, which would have resulted in further costs and delays to the project, the agency said in a written statement.

The money would come from the National Land Transport Fund - a ring-fenced fund covering NZTA spending on its land transport programme.

Relief spending on Transmission Gully would not impact other projects 'currently being progressed' on the state highway network, the NZTA said.

The cash injection would be enough to fund the delayed Cross Valley Link road between Seaview and State Highway 2 three times over, and is the same amount proposed to pay for a new tunnel near the Basin Reserve as part of the Let's Get Wellington Moving programme.

AA motoring affairs general manager Mike Noon said the opening of the route would be great news for regional connectivity.

'But it also provides additional lifelines for the region. I think we really got a wake-up call with the Kaikōura earthquake.'

Noon said unless there was an 'amazingly awful' weather event or earthquake he expected Transmission Gully would be open by Christmas.

The transport fund was 'a little bit underspent' so there was some room to cover the additional cost, he said.

Kāpiti Coast mayor K Gurunathan said the opening announcement was good news, and the additional spending was 'the $190m red carpet to get it done'.

The region had waited decades for the road, which once opened would create massive changes for Kāpiti, he said.

Porirua mayor Anita Baker said the Christmas announcement was good news for the city, which sits beside the southern end of the new road.

'I'm really relieved and I'd like to hold them to that  - that it is open before Christmas.'

She said hopefully that meant the link road connecting Transmission Gully to Kenepuru Dr would be done more quickly too. Work on this route was delayed due to unexpected ground conditions and a rethink on the size of its roundabout.

WELLINGTON TRANSPORT PROJECTS

Transmission Gully: $1.041b

Kāpiti expressway - Mackays to Peka Peka: $649m

Inner-city bypass: $55m

Duplicate Mt Victoria tunnel (proposed): $700m

New Basin Reserve road (proposed): $190m

Kāpiti expressway - Peka Peka to Ōtaki (under construction): $330m

Petone-to-Grenada highway (not funded): $1.06b

Cross Valley Link (not funded): $65m

WHO ARE THEY?

The Transmission Gully Private Public Partnership (PPP) project agreement is between the NZTA and Wellington Gateway Partnership.

WGP is a group of private financiers and contractors who will design, construct, finance and then operate and maintain the new motorway for the 25 years following the construction period.  NZTA is not part of WGP.

- NZTA